1. Project: Hai Thach – Moc Tinh TAR 2025
2) Project Description:
The Bien Dong 1 project involves offshore development of the Hai Thach and Moc Tinh
Gas/Condensate Fields in Blocks 05.2 and 05.3 approximately 340km south of the coast of
Vietnam. The fields lie approximately 20km apart. The Bien Dong 1 project includes:
- A Wellhead platform in Moc Tinh (WHP-MT1);
- A Wellhead platform in Hai Thach (WHP-HT1);
- A Production and Quarter Platform in Hai Thach (PQP-HT);
- A Floating Storage and Offloading (FSO) vessel in Hai Thach;
- An in-field pipeline from the WHP-MT1 to WHP-HT1;
- Condensate export lines from the PQP HT to the FSO;
- A fuel gas line from the PQP HT to the FSO;
- A gas export pipeline from the PQP HT to link up to the existing Nam Con Son
pipeline;
- Submarine Cable from the PQP HT to the WHP-MT.
3. Client: PTSC SUPPLY BASE/ BIENDONG POC
4. End User: BIEN DONG POC
5. 3K's Scope Description: Nitrogen Purging and Leak Test for TAR 2025 (2025)
6. Project Image: