CHEMICAL CLEANING FOR LP BOILER AT CHIM SAO FPSO (2025)

1) Project: LP BOILER C REPAIRE AT  FPSO LEWEK EMAS

2) Project Description:

The Terminal is located in Block 12W offshore Vietnam – about 160n.m south east of Vung Tau. Its exact location is 07°20’39.96”N, 108°18’43.23”N.
Mariners are referred to Admiralty Chart No 3482.

The Terminal acts as offloading terminal for crude oil produced at the Chim Sao and Dua oil fields offshore Vietnam.

The main Field facilities are comprised of the following:

  • a floating production storage and offloading facility;
  • a well head platform;
  • Dua subsea well heads
  • FPSO – Dua subsea well heads pipelines
  • FPSO – WHР infield pipelines; and
  • Gas Offtake pipeline running from FPSO to connect to the Nam Con Son Pipeline system

The Terminal consists of the FPSO Emas Lewek, with the major particulars as follows:
IMO number 7506039
Name of ship Lewek Emas
Call Sign 9V8904
Flag Singapore
MMSI 564 070 000
Gross tonnage 94647
Summer Load line Displacement 211,214
DWT 172,132
Cargo tank capacity excl. Slops 683,024 bbls
Length overall 290.37m
Breadth moulded 50.59m
Depth moulded 23.77m

3. Client: PTSC POS / POVO

4. End User: POVO

5. 3K's Scope Description: Chemical CLeaning for LP Boiler.

6. Project Image: